Status at a glance (14 July 2026 official review): roughly 80 percent complete, with the passenger terminal around three-quarters done. The airfield civil works were completed in December 2025, the first calibration aircraft landed on 4 June 2026, and the operations target announced at the July review is October 2026. An announced target is a plan, not a certification — the status vocabulary on this site keeps that distinction explicit.

Where it is and what it is

The airport is being built at Navagam village, roughly 20 km from the SIR core and about 80 km southwest of Ahmedabad. The site covers around 1,426 hectares, acquired for the purpose. The facility is designed as a Code 4E airport, which in plain terms means a runway and airfield capable of handling wide-body aircraft — the class of machine that matters for cargo capacity and long-haul connectivity alike.

Connectivity from Dholera by air, rail, road and sea: greenfield international airport 15 km, Ahmedabad airport 120 km, expressway and NH links, ports at Pipavav, Kandla, Mundra and proposed Bhavnagar, and DFC freight lines to Delhi and JNPT
The connectivity frame, by mode and distance — Air: greenfield international airport 15 km out, Ahmedabad 120 km, Vadodara 140 km, Bhavnagar 60 km. Rail: freight connectivity with a DFC link at Sanand (100 km) and the Ahmedabad semi-high-speed corridor. Road: the Ahmedabad–Dholera expressway plus NH 751/47, with the Delhi–Mumbai expressway 120 km east. Sea: Pipavav 200 km, Kandla 200 km, Mundra 350 km and a proposed Bhavnagar port at 65 km. Programme-era sheet — panel statuses predate the expressway’s 2026 inauguration and the rail project’s 2026 approval; current status lives in the sections below. Source: DSIRDA/DMICDC material.

Who owns and builds it

Ownership is a three-way public structure through Dholera International Airport Company Ltd (DIACL): the Airports Authority of India holds the majority stake, the Government of Gujarat holds the second-largest share, and NICDIT — the national industrial corridor institution — holds the remainder. That structure matters because it makes the airport a public commitment rather than a private bet: the country’s airport operator has skin in the game.

What is being built

The design divides construction into two parts.

Part A — the airfield civil works: the runway, parallel taxiways, rapid-exit taxiways, aprons, perimeter roads and airside drainage. This part was completed in December 2025.

Part B — the vertical infrastructure: a passenger terminal planned at roughly 20,000 sq m over three levels, a nine-storey air traffic control tower, a cargo complex with temperature-controlled storage and customs facilities, a technical block and an electrical substation.

Artistic recreation of the envisioned Dholera International Airport passenger terminal — a sweeping dome-roofed building with elevated approach corridors and palm-lined access roads
The passenger terminal as envisioned — artistic recreation based on actual site photographs, created for this site (not an official rendering). Part A airfield works were completed in December 2025; the terminal and other vertical works (Part B) are under construction.

The timeline so far

Each dated milestone below links to its intelligence entry with the source and confidence level.

  • January 2024 — the Airports Authority of India awarded the approximately ₹333-crore passenger terminal building contract (reported 5 January 2024). The airport moved into visible construction. (intelligence entry)
  • October 2024 — the Union Cabinet approved the development of the greenfield airport at Dholera: the highest approval rung, closing the approval loop. (intelligence entry)
  • December 2025 — the airfield civil works (Part A) were completed.
  • 4 June 2026 — the AAI carried out the first successful test flight: a calibration aircraft, registration VT-CNS, touched down on the newly constructed runway at Navagam — the first aircraft landing since construction began. (intelligence entry)
  • 14 July 2026 — Union Civil Aviation Minister K. Rammohan Naidu reviewed progress at the site: roughly 80 percent complete, terminal around three-quarters done, October 2026 operations target. (intelligence entry)
  • August 2026 — PIB cleared Ahmedabad Metro Phase 3, with the Dholera airport link moving closer as part of the regional transit picture. (intelligence entry)

What the airport does for the region

Dholera sits on a coastal plain that has no deep port, no mainline railway and, until now, no airport of its own. The airport is meant to do three jobs: give passengers an air link for the SIR and the wider region, give industries an air-cargo channel with customs and temperature-controlled storage on site, and act as a catalyst for airport-linked industrial development — the pattern every successful Indian airport city has followed.

Artistic recreation of Dholera International Airport as envisioned in full operation — aerial view of the terminal, aircraft at the gates, runway and taxiway system with the city skyline behind
The airport as envisioned in full operation — artistic recreation based on actual site photographs, created for this site (not an official rendering). The airfield (Part A) is complete; vertical construction (Part B) is under way.

What an investor should read into this

The path from a calibration flight to commercial operations runs through certification, and that is the step to watch. Calibration flights validate that navigation aids, approach procedures, runway surfaces, lighting and signalling systems behave as designed — the technical groundwork an airport needs before certification. The October 2026 target is an official target, and this page tracks it with the same discipline as every other claim on the site: announced stays announced until something is certified, open and verifiable.

Questions people ask

Where is Dholera International Airport located?

At Navagam village, roughly 20 km from the Dholera SIR core and about 80 km southwest of Ahmedabad, on a site of approximately 1,426 hectares.

When will Dholera International Airport open?

The official operations target is October 2026, announced at the 14 July 2026 ministerial review when the project stood at roughly 80 percent completion. Announced targets are not the same as certified operations.

How complete is the airport?

Roughly 80 percent at the 14 July 2026 review, with the passenger terminal around three-quarters done. The airfield civil works were completed in December 2025.

What aircraft can it handle?

It is designed as a Code 4E facility — a runway and airfield capable of handling wide-body aircraft.

Who owns the airport?

Dholera International Airport Company Ltd (DIACL): the Airports Authority of India holds the majority stake, the Government of Gujarat the second-largest share, and NICDIT the remainder.

When did the first aircraft land?

On 4 June 2026, an AAI calibration aircraft (registration VT-CNS) touched down on the newly constructed runway at Navagam — the first aircraft landing since construction began.