What happened

On 24 October 2013, a single-day batch of four GIDB notifications sanctioned the remaining draft schemes, each “subject to the modifications enumerated in the Schedule” and all signed by CEO A. K. Sharma, published in the Gujarat Government Extraordinary Gazette: DTPS-3 (Sodhi, Sangasar, Panchi, Sandhida, Mundi, Dholera, Otariya, Cher) — SIRAA/06/2013/439; DTPS-4 (Dholera, Mundi, Panchi, Bhangadh, Hebatpur, Zankhi, Mahadevpura, Sandhida) — SIRAA/07/2013/440; DTPS-5 (Sodhi, Sangasar, Panchi, Bavaliyari, Hebatpur) — SIRAA/08/2013/441; and DTPS-6 (Bhangadh, Hebatpur, Zankhi, Bavaliyari, Mingalpur) — SIRAA/09/2013/442.

The background

Each of the four notifications records the paperwork trail beneath it: DSIRDA’s declaration of intention on 5 January 2012, and the draft schemes’ submission to GIDB on 13 December 2012. In other words, the authority had declared, prepared and filed all six schemes well before sanctioning them — the 2013 gazette batch was the formal completion of a process running since the start of 2012.

The details

With this batch, all six parent TP schemes had a complete draft-stage record — the full statutory map of how the activation area and its surroundings would be assembled, village by village. Read the village lists and you are reading the geography of the future city: Dholera and Mundi anchor schemes 3 and 4; Hebatpur and Zankhi anchor 4, 5 and 6; the Bavaliyari and Mingalpur belts extend the frame southward and inward.

The sanctions came with modifications enumerated in each Schedule — the Apex Authority adjusting the drafts DSIRDA had submitted, as the statutory process allows. Draft-stage sanction, it should be noted, is not the operative stage: plots only get reconstituted at the preliminary-scheme stage that followed years later.

Why it matters to Dholera

Why it matters to Dholera: the complete draft record is what made everything after possible — the first operative sanctions (TP 2A/4A in July 2018, sanctioned by CEO Ashwini Kumar), the 3B preliminary sanction of November 2025, and the landmark 30 March 2026 gazette batch in which ten sub-schemes were sanctioned in a single day. Every one of those later instruments cites these 2013 parent schemes as its foundation.

The later life of these six schemes explains why their draft-stage record still matters. Under GTPUDA, a sanctioned draft scheme can be split by the Town Planning Officer into sub-schemes, and that is exactly what happened as Dholera’s priorities sharpened: DTPS-1 was split into sub-schemes 1A1–1A5 and 1B, DTPS-2 into 2A, 2B1, 2B2 and 2B3, and DTPS-3 into 3A, 3B, 3C1 and 3C2. The preliminary sanctions then arrived in waves — 2A and 4A in July 2018, 3B in November 2025, and ten more sub-schemes in a single gazette batch on 30 March 2026 — each citing these 2013 parent sanctions as its legal base.

Reading the four notification numbers together also tells you something about administrative style: Dholera’s land record was built in batches, signed by the authority’s chief executive, and published in Extraordinary Gazettes with the modifications enumerated. That batching is why the whole draft-stage story can be reconstructed from four documents dated one day — a level of statutory tidiness that later made the 2018–2026 sanctions possible without renegotiating the base.

The bigger picture

It is a striking timeline: drafts submitted December 2012, draft sanctions October 2013, first operative sanctions 2018, most preliminary sanctions 2025–2026 — and, as of the latest portal record, the final-scheme stage not yet notified for any scheme. Greenfield land assembly in India moves in statute-years, not news-cycles; Dholera’s investors who understand that cadence read the gazettes, not the headlines.

What came next: the first operative sanction (TP 2A/4A) in July 2018, and the sub-scheme splits of 2025–2026.

Verified sources

This is an archive entry from our milestone backfill — verified against the sources below, with the event date kept true to history.